Question-Answer Plate bearing test,highway constructionwork,and cant

Question-Answer Plate bearing test,highway constructionwork,and cant

Which one of the following tests is carried out using a relatively large diameter plate to evaluate the load supporting capacity of pavement layers?

  • (a) California bearing ratio test
  • (b)California resistance value test
  • (c) Triaxial compression test
  • (d) Plate bearing test


Consider the following aspects of human vision which are important for a traffic engineer:
1. Field of vision
2. Visual acuity
3. Colour perception

Which of the above aspects are correct?

  • (a) 1 and 2 only
  • (b) 2 and 3 only
  • (c) 1 and 3 only
  • (d) 1, 2 and 3


The survey of the highway construction work for preparation of longitudinal and cross sections, computations of earth work quantities; and other construction material and checking details of geometric design elements is carried out in

  • (a) Reconnaissance survey
  • (b) Preliminary survey
  • (c) Location of final alignment
  • (d) Detailed survey


The raising of outer rail over inner rail is called

  • (a) Cant deficiency 
  • (b) Cant
  • (c) Capacity of the track
  • (d) Center bound sleepers




Question-Answer civil engineering study
Question-Answer civil engineering study

QUESTION-ANSWER - CEMENT CONCRETE PAVEMENTS MAXIMUM UTILITY PER UNIT LENGTH AND TUNNELING

QUESTION-ANSWER - CEMENT CONCRETE PAVEMENTS MAXIMUM UTILITY PER UNIT LENGTH AND TUNNELING

Question-Answer

The longitudinal joints in cement concrete pavements are constructed with suitable

  • (a) tie bars
  • (b) torsion rods
  • (c) small spacing
  • (d) shear rods


In which one of the following systems the optimum road length is calculated for an area based on the concept of obtaining maximum utility per unit length of road?

  • (a) Saturation system
  • (b) Unsaturated system
  • (c) Minimum utility system
  • (d) Average utility system


Which one of the following alignments is obtained by development accompanied by tunneling?

  • (a) Valley alignment
  • (b) Cross country alignment
  • (c) Mountain alignment
  • (d) Zig-zag alignment

Question-Answer civil engineering study
Question-Answer civil engineering study

SAFE STOPPING SIGHT DISTANCE AND ECONOMIC DESIGN OF MODERN TRACK

SAFE STOPPING SIGHT DISTANCE AND ECONOMIC DESIGN OF MODERN TRACK

Question-Answer

The design speed for a two-way traffic on a two way lane road is 50 kmph. What is the value of safe stopping sight distance, if co-efficient of friction is 0.37 and reaction time of driver as 2.5 sec?

  • (a) 34.8 m
  • (b) 61.4 m
  • c) 122.8 m
  • (d) 193.5 m


Consider the following statements related to economic design of modern track:

1. Axle loading, possible weight reduction of the rolling stock and increase in number of axles should be rationalized.

2. Rail to sleeper fastenings for different type of sleepers at high speeds should have definite standards.

3. The weight of the sleeper and the rail may not be related to each other. Which of the above statements are correct?

  • (a) 1 and 2 only
  • (b) 2 and 3 only
  • (c) 1 and 3 only
  • (d) 1, 2 and 3


Question-Answer civil engineering study
Question-Answer civil engineering study

Low-altitude aerial photographs, Length of Curve and Long cord

Low-altitude aerial photographs, Length of Curve and Long cord

In multilevel classification system, Level IV classification is suitable for

  • (a) Landsat MSS images
  • (b) High-altitude aerial photographs
  • (c) Low-altitude aerial photographs
  • (d) Medium-altitude aerial photographs

Directions for the following  (02) items:

Read the following information and answer the two items that follow:The chainage of the intersection point of two straights is 1060 m, and the angle of intersection is 120°.  If radius of a circular curve to be set out is 570 m, and peg interval Is 30 m.

What is the length of the curve?

  • (a) 190π m
  • (b) 185π m
  • (c) 180π m
  • (d) 170π m


What is the length of the long chord?

  • (a) 370 m
  • (b) 470 m
  • (c) 670 m
  • (d) 570 m

 


Question-Answer civil engineering study
Question-Answer civil engineering study
In Map versus Aerial photograph, due to symbolic representation the clarity of details is -

In Map versus Aerial photograph, due to symbolic representation the clarity of details is -

Question-Answer:

In Map versus Aerial photograph, due to symbolic representation the clarity of details is

  • (a) less on map than on a photo
  • (b) more on map than on a photo
  • (c) less on a photo than on map
  • (d) more on a photo than on map

next

Question-Answer civil engineering study
Question-Answer civil engineering study

Other Important Topic Related to Surveying in Civil engineering
The levelling is carried out between two stations P and Q separated by 1000 m. The Back Sight (BS) reading is noted as 0.70 m on station P, whose BM is 240.00 m. Next, the Fore Sight (FS) reading is taken on an intermediate point and the value is 1.25 m. Then the instrument is shifted to a new location and BS is taken on intermediate point as 0.85 m. Finally, the FS reading is taken on station Q as 1.10 m. What is the Reduced Level of Q?

The levelling is carried out between two stations P and Q separated by 1000 m. The Back Sight (BS) reading is noted as 0.70 m on station P, whose BM is 240.00 m. Next, the Fore Sight (FS) reading is taken on an intermediate point and the value is 1.25 m. Then the instrument is shifted to a new location and BS is taken on intermediate point as 0.85 m. Finally, the FS reading is taken on station Q as 1.10 m. What is the Reduced Level of Q?

Question-Answer:

The levelling is carried out between two stations P and Q separated by 1000 m. The Back Sight (BS) reading is noted as 0.70 m on station P, whose BM is 240.00 m. Next, the Fore Sight (FS) reading is taken on an intermediate point and the value is 1.25 m. Then the instrument is shifted to a new location and BS is taken on intermediate point as 0.85 m. Finally, the FS reading is taken on station Q as 1.10 m. What is the Reduced Level of Q?

  • (a) 239.20 m
  • (b) 240.80 m
  • (c) 241.25 m
  • (d) 241.80 m

next



Question-Answer civil engineering study
Question-Answer civil engineering study
A line AB between the stations A and B was measured as 348.28 m using a 20 m tape, too short by 0.05 m. What is the correct length of line AB?

A line AB between the stations A and B was measured as 348.28 m using a 20 m tape, too short by 0.05 m. What is the correct length of line AB?

Question-Answer:

A line AB between the stations A and B was measured as 348.28 m using a 20 m tape, too short by 0.05 m. What is the correct length of line AB?

  • (a) 349.15 m
  • (b) 348.41 m
  • (c) 347.41 m
  • (d) 346.15 m

next


Question-Answer civil engineering study
Question-Answer civil engineering study
Which one of the following consists of horizontal and vertical location of certain points by linear and angular measurements and is made to determine the natural features of a country?

Which one of the following consists of horizontal and vertical location of certain points by linear and angular measurements and is made to determine the natural features of a country?

Question-Answer:

Which one of the following consists of horizontal and vertical location of certain points by linear and angular measurements and is made to determine the natural features of a country?

  • (a) Cadastral survey
  • (b) Topographical survey
  • (c) Astronomical survey
  • (d) Military survey

next

Question-Answer civil engineering study
Question-Answer civil engineering study
Which one statements is NOT correct - Trigonometric leveling used in geodetic surveying

Which one statements is NOT correct - Trigonometric leveling used in geodetic surveying

Question-Answer:

Which one of the following statements is NOT correct?

  • (a) Trigonometric levelling has never been used in geodetic surveys
  • (b) The differences in elevation are determined indirectly by trigonometric levelling
  • (c) The electronic distance measurement devices can be used for measuring the vertical distances
  • (d) The combined effects of curvature and refraction produce vertical readings that are slightly too short

next

Question-Answer civil engineering study
Question-Answer civil engineering study
 Dip fault is a fault plane parallel to the dip of beds

Dip fault is a fault plane parallel to the dip of beds

Question-Answer:

 Dip fault is a fault plane

  • (a) parallel to the dip of beds
  • (b) parallel to the strike of a bedding plane
  • (c) diagonal to the dip of a bedding plane
  • (d) with no relationship to the bedding plane

next

Question-Answer civil engineering study